Huston to Gem Transmission Line Upgrade

About the Project

Idaho Power is rebuilding a portion of the transmission line along Chicken Dinner Road to improve reliability and better serve the growing needs of the community.

This project includes upgrading about six miles of line just west of Lake Lowell, between Lewis Lane and Darrow Lane. The existing wood poles will be replaced with new weathered steel poles, and the line will be rebuilt in roughly the same location.

To keep power flowing during construction, the new poles will be installed alongside the existing line before it is removed. The new structures will also be taller, which helps meet modern safety standards and allows space for additional equipment, like lightning protection.

When complete, this upgraded line will provide more reliable service and increase the amount of electricity available to homes, farms, and businesses in the area.

Benefits

Reliable Power


Reduces strain on existing lines to deliver energy safely and consistently when customers need it most.

Meets Demand


Adds capacity to meet increasing energy needs for homes, farms, and businesses.

Manages Costs


Shares resources across regions to reduce the need for additional infrastructure and help keep costs down.

Regional Connectivity


Expands access to domestic energy resources to support a dependable, resilient power supply.

Timeline and Current Status

Construction of this project is complete. Thank you to all our neighbors for your patience as we made this important upgrade.

Frequently Asked Questions

Why doesn’t Idaho Power just build more local energy resources instead of new transmission?

We need both local energy resources and a strong transmission system. Local generation, such as gas fired power plants or solar, helps meet demand close to where it’s used. But transmission lines are what move electricity across the system and ensure it gets where it’s needed, when it’s needed.

Upgrading transmission improves reliability, increases capacity, and allows us to deliver energy more efficiently across the region. It also helps us make the best use of all available energy resources, both local and regional.

Is this new transmission line enabling Idaho Power to sell energy to other states?

No. This project is focused on serving Idaho Power customers here in the Treasure Valley.

While transmission systems are connected across the region, the main purpose of this upgrade is to bring more energy into southern Ada County and Kuna to meet growing local demand and improve reliability—not to export power out of state.

How does Idaho Power work with landowners?

We believe the best projects are built by working closely with the communities we serve.

When a project requires access to land, Idaho Power works directly with property owners to secure easements. An easement allows us to build, operate, and maintain a power line on a portion of private property, while the landowner continues to own and use the land.

We meet with landowners early in the process, explain the project, answer questions, and work one-on-one to reach a fair agreement. Easements typically include compensation and outline how the land can continue to be used.

Are electric and magnetic fields (EMF) dangerous?

Electric and magnetic fields (EMFs) are a natural part of using electricity. They’re present anywhere electricity is flowing such as inside your home, in appliances, and along power lines.

EMFs from transmission lines decrease quickly as you move away from them. At short distances, EMF levels are often similar to, or lower than, what you might experience from common household wiring and devices.

EMFs have been widely studied for decades. Based on this research, EMFs like those from power lines have not been shown to cause harm to people, animals, or crops.

Questions?

If you have questions, contact Jamison Loveless at jloveless@idahopower.com or 208-388-2671.